24 Nov 2020 · Coroner Caroline Beasley-Murray · Essex

The coroner's concerns

  1. 1. lack of approved safe loading and lifting plan

    “Ahead of the incident, there was no approved, safe loading and lifting plan in place and agreed between the two firms”
  2. 2. absence of banksman supervision

    “PCR had not assigned a banksman to supervise the safe loading. Especially in the loading of loads of such weight and size as the balcony frame, there should be a banksman employed”
  3. 3. lack of designated visible area for lorry driver

    “There was no clearly marked designated area established where a lorry driver can be visible at all times. The deployment of cones and signage would have assisted”
  4. 4. lack of correct equipment for safe movement and loading

    “PCR Steel did not have available, from the design stage onwards, the correct equipment to move safely and load the products they manufacture”

Responses

No published response was found on judiciary.uk.

  • Built with
  • NVIDIA Nemotron Nano, Super and Ultra
  • Nebius Token Factory inference
  • Qwen3 Embedding 8B on Token Factory
  • Tavily follow-up web search
  • Postgres and pgvector search
  • Next.js site

Source: Prevention of Future Deaths reports and responses published by the Courts and Tribunals Judiciary at judiciary.uk. Crown copyright, used under the Open Government Licence v3.0. Data updated 26 Oct 2026.

A link shows that a similar concern was raised again, not why. It is not a finding about any organisation or person. Methodology and responsible use · Report an error